The order a crew works in on a Queens roof, and why: the layout walked first, the attachments before the rails, the wiring last, and the system left off until the utility says yes.
AI-generated illustration. Not a real home or business.
The job in nine steps
One of them comes before the crew arrives and two in the weeks after it; the six in between are the day itself.
Before the day
The permits are issued, the materials are on their way, and you have the signed contract, the State's disclosure form and the layout. Someone is home to let the crew through to the roof and the basement.
The crew arrives
The crew lead walks the roof with you against the layout: where the panels go, where the clear paths stay, where the wiring comes down the back wall.
Up to the roof
Everything goes up through the bulkhead or the hatch, or by ladder from the yard, and the crew ties off to a safety line before anyone works near an edge.
The attachments
On a shingle roof each attachment is fixed into a rafter and sealed under a metal flashing; on a standing-seam metal roof the rails clamp to the seams, with no hole through the roof; on a flat roof the frames sit on pads laid on the roof, or the canopy's feet go where the drawing puts them.
Rails and panels
The rails or the frames are set out around the clear paths, and the panels are lifted and clamped one by one.
The wiring
Under the panels, then in conduit down the back of the house to the meter and the panel in the basement, with a shut-off and the warning labels the code requires.
The tie-in
A short power cut at the end of the day, while the system is connected to the house's panel. The system stays off.
Inspections
An independent inspector and the Department of Buildings' electrical inspector check the work, usually in the weeks after.
Permission to operate
The utility reviews the job and changes the meter's settings. Only then is the system switched on and the monitoring set up, and only then does the last stage fall due.
Why it goes in this order
Ruairi Delacroix-Amadi leads the crews on flat and sloped roofs across Queens. He walks the roof with the layout in hand before any racking is carried up. A layout is drawn from measurements; the walk is where it meets the real roof, with you there to say which part of the roof you use and what on it matters to you.
The attachments go in before the rails or the frames, because they decide where everything else sits. On a sloped roof each one is found in a rafter and sealed before the next is drilled; on a flat roof the pads go down first, or the canopy's feet where the drawings put them.
Yusuf Kristiansen-Bell puts up the raised canopies over flat roofs. He sets each of the canopy's feet where the drawings put it, and checks it against the plan. He leaves the walkway under the canopy as clear as the day he arrived.
The wiring runs under the panels and then in conduit down the back of the house, away from the street and out of the walkway. The tie-in comes last, and the system is left switched off: it is finished, but it may not run until the inspections are done and the utility has given its permission.
AI-generated illustration. Not a real person, home or business.
When the crews are on the roof
The crews are on the roof from 8 am to 4 pm, Monday to Friday, and come down in high wind, rain, ice or lightning: a roof day lost to weather is moved, never rushed.
No survey or install is done on a weekend or on a federal holiday: New Year's Day, Martin Luther King Jr. Day, Washington's Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving or Christmas Day, or the day any of them is observed.
Your part of the day
Five things, and each of them makes the crew's part simpler.
Be there when the crew arrives, or have someone there who can answer for you.
Walk the layout with the crew lead, and say if anything on the roof matters to you.
Leave the system switched off until the utility has given its permission; the office tells you when.
Keep the warning labels and the shut-off clear: they are for the fire department.
Look at the roof with the crew lead before they leave.
After the day
From a signed contract to a system the utility lets you switch on usually takes two to four months in New York City: the drawings and the permits, the install itself in a day or two, the inspections, and the utility's own review. A landmark review or a fire department variance adds weeks.
As of October 2026, Con Edison customers who add solar are credited for what they send to the grid under net metering, and pay a monthly charge for the system's size, the Customer Benefit Contribution, that changes every year. The installer applies to the utility in your name, and the system runs only after the utility gives permission to operate.